slava.energy: UK renewable energy projects
Vauxhall Motors
REPD record 5641. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Abandoned
- Operator
- PerPetum Sun
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- Central Bedfordshire
- Planning reference
- CB/15/03550/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-01-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-09-21: Planning Application Submitted
- 2015-11-05: Planning Permission Granted
- 2018-11-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5641. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.