Land at Bluehouse Farm
REPD record 5656. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Anesco
- County
- Cleveland
- Region
- North East
- Country
- England
- Planning authority
- Hartlepool
- Planning reference
- H/2015/0316
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-12-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-09-09: Planning Application Submitted
- 2015-11-30: Planning Permission Granted
- 2016-06-15: Under Construction
- 2016-08-31: Operational
- 2018-11-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5656. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.