slava.energy: UK renewable energy projects
North Wharf Solar Farm
REPD record 5661. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 6 MW
- Status
- Appeal Refused
- Operator
- North Wharf Solar Farm
- County
- Humberside
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- North Lincolnshire
- Planning reference
- PA/2015/0942
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-11-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-09-10: Planning Application Submitted
- 2015-11-18: Planning Permission Refused
- 2016-03-18: Appeal Lodged
- 2016-10-17: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5661. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.