slava.energy: UK renewable energy projects
Land North of Marlow Landfill Site
REPD record 5684. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Planning Permission Refused
- Operator
- Anesco
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 15/07001/FULEA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-03-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-09-07: Planning Application Submitted
- 2016-02-26: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5684. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.