Pilsworth Quarry Landfill Scheme
REPD record 571. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 4.1 MW
- Status
- Operational
- Operator
- Terry Adams Ltd
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Bury
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2009-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 1997-12-15: Planning Application Submitted
- 1998-05-19: Planning Permission Granted
- 1998-10-15: Operational