Great Tong Solar Farm
REPD record 5729. Status: Appeal Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Appeal Withdrawn
- Operator
- Solar Securities
- County
- Kent
- Region
- South East
- Country
- England
- Planning authority
- Maidstone
- Planning reference
- 15/505974/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-08-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-24: Planning Application Submitted
- 2016-02-29: Planning Permission Refused
- 2016-12-21: Appeal Lodged
- 2017-01-10: Appeal Withdrawn
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5729. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.