Brookhouse Farm
REPD record 5731. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Appeal Refused
- Operator
- Earthworm Energy
- County
- Hereford and Worcester
- Region
- West Midlands
- Country
- England
- Planning authority
- Herefordshire, County of
- Planning reference
- P152188/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-09-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-21: Planning Application Submitted
- 2015-11-20: Planning Permission Refused
- 2016-05-31: Appeal Lodged
- 2016-08-23: Appeal Refused