slava.energy: UK renewable energy projects

The Sawmill

REPD record 5753. Status: Revised.

Facts

As published by REPD, release Q3 2026.

Technology
Biomass (dedicated)
Capacity
3 MW
Status
Revised
Operator
John Brooke Sawmills
County
Nottinghamshire
Region
East Midlands
Country
England
Planning authority
Rushcliffe
Planning reference
F/1908
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2015-10-15

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5753. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.