Park Farm
REPD record 5786. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- BNRG (BL Solar)
- County
- West Sussex
- Region
- South East
- Country
- England
- Planning authority
- Arun
- Planning reference
- P/81/15/PL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-04-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-07-23: Planning Application Submitted
- 2015-10-29: Planning Permission Granted
- 2015-12-15: Under Construction
- 2016-03-24: Operational
- 2018-10-29: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5786. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.