slava.energy: UK renewable energy projects
Tamerton Road
REPD record 5810. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Revised
- Operator
- Roborough Solar
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Plymouth
- Planning reference
- 04/2253/15/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-08-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-10-14: Planning Application Submitted
- 2016-03-10: Planning Permission Granted
- 2019-03-10: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5810. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.