slava.energy: UK renewable energy projects

Two Oaks Quarry

REPD record 5840. Status: Planning Permission Expired.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
5 MW
Status
Planning Permission Expired
Operator
Mansfield Sand
County
Nottinghamshire
Region
East Midlands
Country
England
Planning authority
Ashfield
Planning reference
V/2015/0589
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2020-08-11

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5840. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.