slava.energy: UK renewable energy projects
Newport (Began Road)
REPD record 5866. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Operational
- Operator
- Eco Energy World
- County
- Gwent
- Region
- Wales
- Country
- Wales
- Planning authority
- Newport
- Planning reference
- 14/0337
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-04-03: Planning Application Submitted
- 2015-10-22: Planning Permission Granted
- 2015-12-14: Under Construction
- 2016-02-14: Operational
- 2020-10-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5866. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.