slava.energy: UK renewable energy projects
Woodington Solar Farm
REPD record 5883. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 46 MW
- Status
- Under Construction
- Operator
- Woodington Solar Limited
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 15/02591/FULLS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-01-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-11-17: Planning Application Submitted
- 2017-07-04: Planning Permission Granted
- 2020-05-15: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5883. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.