Mill Farm
REPD record 5887. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Push Energy& NextEnergy Solar Fund (NESF)
- County
- Hertfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- East Hertfordshire
- Planning reference
- 3/15/2254/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-04-18
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-11-09: Planning Application Submitted
- 2016-07-20: Planning Permission Granted
- 2016-12-15: Operational
- 2017-01-04: Under Construction
- 2019-07-20: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5887. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.