Highlee Hill Wind Farm
REPD record 5912. Status: Planning Application Withdrawn.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 44.9 MW
- Status
- Planning Application Withdrawn
- Operator
- Renewable Energy Systems (RES)
- County
- Scottish Borders
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Borders
- Planning reference
- 16/00810/FUL
- Turbines
- 13
- Turbine size
- 3.45 MW
- Record last updated in REPD
- 2017-06-01
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-07-01: Planning Application Submitted
- 2017-05-11: Planning Application Withdrawn
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5912. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.