Fort Industrial Park (Castle Bromwich)
REPD record 5959. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 10.2 MW
- Status
- Planning Permission Granted
- Operator
- Industrial Property Investment Fund
- County
- West Midlands
- Region
- West Midlands
- Country
- England
- Planning authority
- Birmingham
- Planning reference
- 2015/09679/PA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-04-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-12-10: Planning Application Submitted
- 2016-06-24: Planning Permission Granted
- 2019-06-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5959. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.