slava.energy: UK renewable energy projects
Airport Road West
REPD record 5995. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Belfast Harbour Commissioners
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Belfast
- Planning reference
- LA04/2016/0057/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-12-18: Planning Application Submitted
- 2016-04-22: Planning Permission Granted
- 2016-12-30: Under Construction
- 2017-03-30: Operational
- 2021-04-21: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 5995. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.