slava.energy: UK renewable energy projects
St Philips Marsh
REPD record 6025. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 20 MW
- Status
- Appeal Refused
- Operator
- Plutus Energy
- County
- Avon
- Region
- South West
- Country
- England
- Planning authority
- Bristol, City of
- Planning reference
- 16/00719/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-06-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-02-10: Planning Application Submitted
- 2016-10-04: Planning Permission Refused
- 2017-03-24: Appeal Lodged
- 2017-06-28: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6025. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.