Clifton Marsh Wwtw
REPD record 6034. Status: Planning Permission Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.5 MW
- Status
- Planning Permission Refused
- Operator
- United Utilities
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- Fylde
- Planning reference
- LCC/2016/0007
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-01-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-01-22: Planning Application Submitted
- 2017-01-20: Planning Permission Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6034. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.