slava.energy: UK renewable energy projects
Burnside Farm Biomass Plant
REPD record 61. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 2.5 MW
- Status
- Abandoned
- Operator
- Border Biofuels
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- North Ayrshire
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2006-06-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2001-06-26: Planning Application Submitted
- 2001-10-08: Planning Permission Granted
- 2003-10-08: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 61. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.