slava.energy: UK renewable energy projects
Waltham Point Distribution Centre
REPD record 6114. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1.8 MW
- Status
- Operational
- Operator
- Sainsburys Supermarkets Limited
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Epping Forest
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2016-05-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-01-05: Under Construction
- 2016-02-05: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6114. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.