slava.energy: UK renewable energy projects
Higher Humber Farm
REPD record 6130. Status: Appeal Refused.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5.9 MW
- Status
- Appeal Refused
- Operator
- TGC Renewables
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Teignbridge
- Planning reference
- 14/03725/MAJ
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-01-06: Planning Application Submitted
- 2016-04-05: Planning Permission Refused
- 2016-05-12: Appeal Lodged
- 2017-02-09: Appeal Refused
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6130. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.