slava.energy: UK renewable energy projects
Land East of Horton Road
REPD record 6133. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4.9 MW
- Status
- Operational
- Operator
- NESF (formerly Lark Energy)
- County
- Northamptonshire
- Region
- East Midlands
- Country
- England
- Planning authority
- West Northamptonshire
- Planning reference
- S/2014/2075/MAF
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-07-05
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-10-20: Planning Application Submitted
- 2015-05-01: Planning Permission Granted
- 2016-01-31: Under Construction
- 2017-07-07: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6133. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.