slava.energy: UK renewable energy projects
Tully Quarry
REPD record 6134. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 3 MW
- Status
- Operational
- Operator
- Stream Bioenergy
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Mid and East Antrim
- Planning reference
- G/2013/0282/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-12-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-07-31: Planning Application Submitted
- 2013-12-17: Planning Permission Expired
- 2013-12-17: Planning Permission Granted
- 2016-06-21: Under Construction
- 2017-07-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6134. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.