slava.energy: UK renewable energy projects

Grove Solar Park (Phase 2)

REPD record 6163. Status: Operational.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
11 MW
Status
Operational
Operator
Solar Century
County
Hampshire
Region
South East
Country
England
Planning authority
Test Valley
Planning reference
14/01826/FULLS
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2017-01-16

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Other REPD records on the same site

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6163. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.