Bumpers Farm Phase 2
REPD record 6282. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 12 MW
- Status
- Appeal Granted
- Operator
- Anesco
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Buckinghamshire
- Planning reference
- 14/01926/APP
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-06-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2014-07-11: Planning Application Submitted
- 2014-09-05: Planning Permission Refused
- 2015-02-04: Appeal Lodged
- 2015-10-26: Appeal Granted
- 2015-10-26: Planning Permission Granted
- 2018-10-26: Planning Permission Expired