slava.energy: UK renewable energy projects
High Meadow Farm
REPD record 6321. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 4 MW
- Status
- Operational
- Operator
- Anesco
- County
- County Durham
- Region
- North East
- Country
- England
- Planning authority
- Stockton-on-Tees
- Planning reference
- 15/1826/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2017-02-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-12-04: Planning Permission Expired
- 2015-07-22: Planning Application Submitted
- 2015-12-04: Planning Permission Granted
- 2016-08-18: Under Construction
- 2016-10-18: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6321. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.