Deep Moor Landfill Site
REPD record 6328. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 2 MW
- Status
- Operational
- Operator
- Coastal Recycling UK (formerly Devon Waste Management)
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- Torridge
- Planning reference
- DCC/3848/2016
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-06-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-03-09: Planning Application Submitted
- 2017-02-02: Planning Permission Granted
- 2018-03-15: Under Construction
- 2018-04-20: Operational
- 2029-02-02: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6328. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.