Swindon Energy Plant (Park Grounds)
REPD record 6396. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 6 MW
- Status
- Under Construction
- Operator
- Advanced Biofuel Solutions (formerly Crapper and Sons Landfill)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 17/03547/WCM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-09-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-04-07: Planning Application Submitted
- 2017-06-15: Planning Permission Granted
- 2018-06-15: Under Construction
- 2020-08-02: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6396. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.