Graig Fatha Farm
REPD record 6422. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 2.5 MW
- Status
- Operational
- Operator
- Cleanearth
- County
- Rhondda Cynon Taff
- Region
- Wales
- Country
- Wales
- Planning authority
- Rhondda Cynon Taf
- Planning reference
- 17/0493/10
- Turbines
- 1
- Turbine size
- 2.5 MW
- Record last updated in REPD
- 2023-03-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-05-02: Planning Application Submitted
- 2017-06-15: Planning Permission Granted
- 2021-10-01: Under Construction
- 2021-12-01: Operational
- 2023-03-14: Planning Permission Expired