Glenshimmeroch Wind Farm
REPD record 6444. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 36 MW
- Status
- Appeal Granted
- Operator
- Energiekontor UK
- County
- Dumfries and Galloway
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Dumfries and Galloway
- Planning reference
- 18/0992/FUL
- Turbines
- 10
- Turbine size
- 3.6 MW
- Record last updated in REPD
- 2024-01-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-07-02: Planning Application Submitted
- 2019-02-22: Appeal Lodged
- 2019-03-05: Planning Permission Refused
- 2019-09-04: Appeal Granted
- 2019-09-04: Planning Permission Granted
- 2022-09-04: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6444. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.