Branston Solar Park (extension)
REPD record 6456. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 40 MW
- Status
- Under Construction
- Operator
- Ethical Power
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Kesteven
- Planning reference
- 17/1546/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-11-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-12-19: Planning Permission Expired
- 2017-10-23: Planning Application Submitted
- 2017-12-19: Planning Permission Granted
- 2019-09-30: Under Construction