slava.energy: UK renewable energy projects
Longlands Farm, Rush Wall Lane
REPD record 6509. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 3.5 MW
- Status
- Operational
- Operator
- Clean Earth (CE)
- County
- Gwent
- Region
- Wales
- Country
- Wales
- Planning authority
- Newport
- Planning reference
- 18/0408
- Turbines
- 1
- Turbine size
- 3.5 MW
- Record last updated in REPD
- 2024-02-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-05-03: Planning Application Submitted
- 2020-10-01: Under Construction
- 2021-01-01: Operational
- 2024-01-09: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6509. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.