Clifton Marsh Wastewater Treatment Works
REPD record 6523. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.2 MW
- Status
- Operational
- Operator
- United Utilities Water& Preston City Council
- County
- Lancashire
- Region
- North West
- Country
- England
- Planning authority
- Fylde
- Planning reference
- LCC/2017/0090
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-09-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-11-23: Planning Application Submitted
- 2018-08-23: Planning Permission Granted
- 2019-01-15: Under Construction
- 2019-08-22: Operational
- 2021-12-07: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6523. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.