High Parkfoot Farm
REPD record 6588. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 20 MW
- Status
- Planning Permission Granted
- Operator
- Elgin Energy
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Cumberland
- Planning reference
- 18/0197
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-03-12: Planning Application Submitted
- 2022-07-21: Planning Permission Granted
- 2025-07-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6588. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.