Rampton Hospital Energy Centre
REPD record 66. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- Cofely
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Bassetlaw
- Planning reference
- 12/01799/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2015-06-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-12-24: Planning Application Submitted
- 2013-02-06: Planning Permission Granted
- 2014-02-06: Planning Permission Expired
- 2015-02-01: Under Construction
- 2015-05-29: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 66. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.