slava.energy: UK renewable energy projects
Broadley Copse
REPD record 6626. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 2.2 MW
- Status
- Operational
- Operator
- Broadley Energy
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Chichester
- Planning reference
- SDNP/15/04189/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-05-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-08-18: Planning Application Submitted
- 2016-02-29: Planning Permission Granted
- 2017-03-24: Under Construction
- 2018-03-24: Operational
- 2019-04-06: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6626. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.