Brynpica Landfill Site
REPD record 665. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 2.7 MW
- Status
- Operational
- Operator
- NOVERA
- County
- Mid Glamorgan
- Region
- Wales
- Country
- Wales
- Planning authority
- Rhondda Cynon Taf
- Planning reference
- 03/0026
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2010-04-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2003-01-09: Planning Application Submitted
- 2003-03-20: Planning Permission Granted
- 2003-08-01: Operational
- 2012-03-20: Planning Permission Expired
Open this area on the map