Broken Cross (Former Surface Mine)
REPD record 6708. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 48 MW
- Status
- Operational
- Operator
- Baywa R.E. UK Limited
- County
- Lanarkshire
- Region
- Scotland
- Country
- Scotland
- Planning authority
- South Lanarkshire
- Planning reference
- P/19/1636
- Turbines
- 10
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-01-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-10-30: Planning Application Submitted
- 2020-04-21: Planning Permission Granted
- 2023-07-01: Under Construction
- 2024-04-22: Planning Permission Expired
- 2024-10-01: Operational
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6708. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.