slava.energy: UK renewable energy projects

Kingston Park

REPD record 6712. Status: Planning Permission Expired.

Facts

As published by REPD, release Q3 2026.

Technology
Solar Photovoltaics
Capacity
1.8 MW
Status
Planning Permission Expired
Operator
Amazon UK Services & Push Energy
County
Cambridgeshire
Region
Eastern
Country
England
Planning authority
Peterborough
Planning reference
18/01311/FUL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2020-02-04

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6712. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.