Bilbo Solar Farm
REPD record 6736. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 36.6 MW
- Status
- Under Construction
- Operator
- Green Energy International
- County
- Aberdeenshire
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2019/0296
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-10-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-06-26: Planning Application Submitted
- 2019-11-15: Planning Permission Granted
- 2020-12-01: Under Construction
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6736. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.