slava.energy: UK renewable energy projects
Lodge Hill, Berkley - Solar Park
REPD record 6797. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 14.5 MW
- Status
- Planning Permission Granted
- Operator
- Wessex Solar Energy Limited
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2021/2191/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-11-24: Planning Application Submitted
- 2022-10-21: Planning Permission Granted
- 2027-10-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6797. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.