slava.energy: UK renewable energy projects
402 metres NE of 45 Dickeystown Road
REPD record 6801. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Wind Onshore
- Capacity
- 0.3 MW
- Status
- Appeal Granted
- Operator
- Glenview Green Energy
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Mid and East Antrim
- Planning reference
- LA02/2017/0715/F
- Turbines
- 1
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-01-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-08-04: Planning Application Submitted
- 2018-08-22: Planning Permission Refused
- 2018-09-26: Appeal Lodged
- 2019-03-28: Appeal Granted
- 2019-03-28: Planning Permission Granted
- 2024-03-28: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6801. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.