Bryn-Y-Plentyn Farm
REPD record 6817. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.5 MW
- Status
- Planning Permission Expired
- Operator
- CR and GM Woollam
- County
- Shropshire
- Region
- West Midlands
- Country
- England
- Planning authority
- Shropshire
- Planning reference
- 18/05499/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-11-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-11-28: Planning Application Submitted
- 2019-02-20: Planning Permission Granted
- 2022-10-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6817. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.