Colony Farm
REPD record 6824. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 4 MW
- Status
- Under Construction
- Operator
- Private Developer
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Fenland
- Planning reference
- F/YR18/0908/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-07-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2018-10-05: Planning Application Submitted
- 2018-12-21: Planning Permission Granted
- 2019-03-01: Under Construction
- 2022-02-27: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6824. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.