slava.energy: UK renewable energy projects
South Antrim Solar Park - Phase 2
REPD record 6829. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 39.5 MW
- Status
- Planning Permission Granted
- Operator
- Hadstone Energy
- County
- Co. Antrim
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Antrim and Newtownabbey
- Planning reference
- LA03/2015/0262/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-07-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2015-06-30: Planning Application Submitted
- 2016-04-25: Planning Permission Granted
- 2021-04-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6829. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.