Coire Glas - Phase I
REPD record 6870. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Pumped Storage Hydroelectricity
- Capacity
- 600 MW
- Status
- Revised
- Operator
- SSE Renewables
- County
- Highland
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- EC00003164
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-08-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-02-10: Planning Application Submitted
- 2021-12-12: Planning Permission Expired