Tynemouth Energy Storage System (TESS)
REPD record 6925. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 25 MW
- Status
- Operational
- Operator
- Enel (formerly Element Power)
- County
- Tyne and Wear
- Region
- North East
- Country
- England
- Planning authority
- North Tyneside
- Planning reference
- 16/01451/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-08-03
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-09-08: Planning Application Submitted
- 2018-05-25: Operational
- 2018-12-20: Under Construction
- 2019-10-12: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6925. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.