REPD record 6932. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 23.4 MW
- Status
- Operational
- Operator
- UK Power Reserve
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Melton
- Planning reference
- 16/00522/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-04-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2016-08-01: Planning Application Submitted
- 2016-09-30: Planning Permission Granted
- 2018-06-08: Under Construction
- 2019-04-01: Operational
- 2019-09-30: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 6932. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.