Claredown Farm
REPD record 6945. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 20 MW
- Status
- Operational
- Operator
- Zenobe (formerly Energy Reservoir 15)
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Braintree
- Planning reference
- 17/00583/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-11-26
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-04-04: Planning Application Submitted
- 2017-08-02: Planning Permission Granted
- 2017-09-01: Under Construction
- 2018-02-27: Operational
- 2023-08-02: Planning Permission Expired